Skip to primary navigation | Skip to sub navigation | Skip to content | Skip to footer

Maluka Views Subdivision

Maluka Views Subdivision, Darwin, NT
project details
Location:
Palmerston CBD, NT
Client:
Mibro (NT) Pty Ltd
Contract Value:
$5.54M
Commencement Date:
17 May 2016
Completion Date:
23 December 2016
Referees:
Cameron Bowes, MiBro

Sitzler partnered with the developer to prepare a submission for the rights to redevelop this under-utilised site on the fringe of the Palmerston CBD into an integrated high density subdivision.

Sitzler managed all aspects of the design coordinating the civil, hydraulic, electrical, landscaping consultants to obtain approval by relevant authorities. Sitzler managed the construction, commissioning and handover of new infrastructure, self-performing the civil works and engaging specialist sub-contractors for plumbing, electrical and landscaping works.

The project was delivered on time and on budget, with minimal disruption to the neighbouring properties through consultation with key stakeholders including: local residents; hotel operator; other contractors undertaking works adjacent to the site; Department of Environment and Natural Resources; Department of Infrastructure Planning and Logistics; Power Water; Telstra; NBN and Palmerston City Council.

Sitzler achieved Practical Completion of NBN upon first inspection without defects. This was the first time a contractor in the Darwin region had achieved this feat.